Renovation of 2,200 m² - Integrated photovoltaic roofing of 77 kwc.

INFORMATION SHEET:

Date of completion June 2009
Owner Idelux
Architect Samyn & Partners
Engineering office Arcadis
Construction enterprise Duchêne
Electrician Nizet
Area 2200 m²

 

Renovation

Isolation Recticel Eurothane Silver 70 mm
Waterproofing SIKAPLAN 20G 2 mm
Solar cells SolarIntegrated Si-G2 576
Installed Power 77.3 Kwc
Annual Power 790.3 Kwh
Total weight 10 kg/m²